Alameda County Battery storage and data center rules.
- Battery storageNo battery-specific rules
- Data centersNo data center rules
Battery storage
- Key rules
- No zoning ordinance allows standalone battery storage, per the Planning Director's Dec 1, 2025 briefing to the Board's Transportation/Planning Committee. East County land also falls under Measure D.
- Pending action
- The Planning Department is drafting a General Plan Amendment and zoning ordinance to allow battery storage and solar under the East County Area Plan; until it is adopted the county cannot formally process battery applications (committee minutes, Feb 2, 2026). Staff expected outreach to start within 60 days and CEQA review to take four to six months, and were asked to report back in about six months. No draft or hearing date found.
- Projects
- Opt-in: Potentia-Viridi (Levy Alameda LLC, 400 MW/3,200 MWh; 24-OPT-04) approved by the CEC May 26, 2026, now pre-construction with a June 2028 online date; Viracocha-Hill (Reclaimed Wind LLC, 90.7 MW/362.8 MWh; 25-OPT-01) under review, application found incomplete Nov 14, 2025. CAISO files Potentia-Viridi under San Joaquin County. CAISO queue: 5 active storage entries (1,337 MW), incl. Espresso, Spectrum Energy Storage, Zorin Storage; 1 completed.
- Sources
Data centers
- Key rules
- Title 17 (Zoning) and the building and business titles do not mention data centers (GoCodebook copy).
- Pending action
- None found in agenda, CEQAnet or news searches.
- Projects
- In Hayward: STACK's SVY03A campus received a CEC small power plant exemption (May 2025).
- Sources
A brief on Alameda County.