San Diego County Battery storage and data center rules.

Battery storage

Draft rulesChecked Nov 16, 2026

Key rules
No BESS zoning standards adopted. County Fire interim guidelines (May 15, 2025) set 100 ft from residential, institutional and school buildings and 10 ft between enclosures. Board rejected a countywide moratorium in Sept 2024.
Pending action
Draft BESS Zoning Ordinance Amendment was out for public comment Aug 13 to Sept 27, 2026; Planning Commission and Board dates not posted.
Projects
Starlight Solar (Boulevard; 100 MW solar, 217.4 MW/868 MWh storage) approved by the Board 5-0 on Sept 16, 2026; a CEQA suit filed Oct 15, 2026 is pending. AES Seguro (Escondido area) drew the 2024 moratorium push. CAISO queue: 8 active storage entries (1,361 MW), incl. Desert Jewel Storage, East Field Energy Storage, Gateway Energy Storage 2; 14 completed.
Sources

Data centers

No data center rulesChecked Nov 16, 2026

Key rules
The Zoning Ordinance has no data center use type. The county says a large-scale data center would be classed as Major Impact Services and Utilities and need a Major Use Permit, with environmental review and public hearings.
Pending action
The July 14, 2026 report back to the Board lists options, including a formal determination on that classification and a zoning definition for data centers. Further action needs a new public hearing; none is scheduled.
Projects
No data centers of any size and no complete data center Use Permit applications in the unincorporated county (July 14, 2026).
Sources

A brief on San Diego County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.