San Joaquin County Battery storage and data center rules.
- Battery storageNo battery-specific rules
- Data centersMoratorium
Battery storage
- Key rules
- Development Title Sec. 9-901 lists battery storage facilities as a typical Utility Services, Major use, with no BESS-specific standards (GoCodebook copy, Oct 2026 edition). Projects use Site Approvals or Administrative Use Permits.
- Pending action
- None found in CEQAnet or news searches.
- Projects
- Griffith Energy Storage (400 MW, Site Approval PA-2200137) approved Mar 12, 2024. A 40 MW/320 MWh BESS near Tracy (PA-2400335) approved July 11, 2025. The CEC approved the Potentia-Viridi opt-in BESS May 26, 2026; CAISO files it here and the CEC places it in Alameda County. CAISO queue: 8 active storage entries (2,001 MW), incl. Alta Casa Storage, Denali Energy Storage, Noosa Energy Storage, Pathfinder Storage; 3 completed.
- Sources
Data centers
- Key rules
- A 45-day moratorium on land-use approvals for data centers in the unincorporated county, adopted 5-0 on Oct 6, 2026. The county says it has no standards for data center noise, energy demand, emergency response or infrastructure capacity.
- Pending action
- Ends about Nov 20, 2026 unless the Board extends it; an extension can run 10 months 15 days. We have not found an extension item.
- Projects
- No applications and no data centers in the unincorporated county (county release, Sept 1, 2026).
- Sources
A brief on San Joaquin County.
A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.
Request this briefSee the six productsSolano County sample brief (PDF)