Santa Barbara County Battery storage and data center rules.

Battery storage

Ordinance in forceChecked Nov 16, 2026

Key rules
The Utility-Scale Solar Amendments (24ORD-00028 to 00030) passed first reading 4-1 on Sept 1, 2026, with final reading set for Sept 22; supporters said the county finalized them that week. They allow standalone battery storage in the unincorporated county, require a 50-foot setback from sensitive receptors such as schools and homes for solar and battery projects of half an acre or more, and cap large solar at 16,000 acres countywide. County ordinances take effect 30 days after final passage, about Oct 22, 2026; Coastal Zoning Ordinance changes also need Coastal Commission certification.
Pending action
The county has not posted the adopted ordinance numbers, effective date or battery permit tiers online; confirm them with Planning and Development before relying on this row.
Projects
In the city of Goleta, Scale Microgrids' 30 MW Greenbark 30 BESS released a draft mitigated negative declaration in December 2025. CAISO queue: no storage entries.
Sources

Data centers

No data center rulesChecked Nov 16, 2026

Key rules
The Land Use and Development Code, Coastal Zoning Ordinance and Montecito code and the building and business titles do not mention data centers (GoCodebook copy, Oct 2026 edition).
Pending action
None found in agenda, CEQAnet or news searches.
Projects
None found in CEQAnet since 2021.
Sources

A brief on Santa Barbara County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.

Request this briefSee the six productsSolano County sample brief (PDF)