Santa Cruz County Battery storage and data center rules.

Battery storage

No battery-specific rulesChecked Nov 16, 2026

Key rules
No BESS rules in force. On June 30, 2026 the Board voted 5-0 to set aside its draft Energy Storage System Combining District (Sec. 13.10.408), approved as a draft Jan 13, 2026, after the Seahawk developer moved to the state opt-in path. The county will ask the CEC to use the draft as a guide.
Pending action
None scheduled; the set-aside draft has no hearing date.
Projects
Opt-in: Seahawk BESS (200 MW/800 MWh at 90 Minto Rd near Watsonville; 26-OPT-02). New Leaf Energy withdrew its county application in May 2026 and applied to the CEC, and Invenergy announced in August 2026 that it had bought the project. The CEC found the application incomplete July 8, 2026. Opposed by Stop Lithium BESS in Santa Cruz County. CAISO queue: 1 active storage entry (204 MW), incl. Seahawk Storage.
Sources

Data centers

No data center rulesChecked Nov 16, 2026

Key rules
Title 13 (Planning and Zoning) and the building and business titles do not mention data centers (GoCodebook copy).
Pending action
On Sept 15, 2026 the Board voted 3-2 against a proposal to let voters decide on AI data centers in the unincorporated county.
Projects
None found in CEQAnet since 2021.
Sources

A brief on Santa Cruz County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.