Stanislaus County Battery storage and data center rules.
- Battery storageNo battery-specific rules
- Data centersNo data center rules
Battery storage
- Key rules
- Title 21 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Use Permit in General Agriculture (Saltgrass, A-2-40).
- Pending action
- Saltgrass Energy Storage (162 MW/650 MWh, PLN2025-0075) in early consultation since Jan 2, 2026. Amanece Hybrid Solar (400 MW, PLN2026-0068) entered early consultation Oct 22, 2026.
- Projects
- TID and MID areas sit outside the CAISO queue. CAISO queue: 2 active storage entries (385 MW), incl. Crow Creek Solar 1, Golden Flats; 2 completed.
- Sources
Data centers
- Key rules
- Title 21 (Zoning) and the building and business titles do not mention data centers (GoCodebook copy, Oct 2026 edition).
- Pending action
- None found in agenda, CEQAnet or news searches.
- Projects
- Patterson (city) adopted a 45-day data center moratorium July 16, 2026.
- Sources