Tehama County Battery storage and data center rules.

Battery storage

No battery-specific rulesChecked Nov 15, 2026

Key rules
Title 17 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).
Pending action
None found in CEQAnet or news searches.
Projects
No county BESS projects in CEQAnet since 2023. CAISO queue: no storage entries.
Sources

Data centers

Draft rulesChecked Nov 16, 2026

Key rules
Chapter 17.34 lists data centers as a permitted use in the M-1 Light Industrial zone, with no data center standards.
Pending action
Rezone #26-03, requested by the Board, would move data centers from permitted to Conditional Use Permit in M-1. Staff will take it to the Planning Commission and then the Board; the CEQA exemption was filed Nov 16, 2026. No hearing date is posted.
Projects
None found in CEQAnet since 2021.
Sources

A brief on Tehama County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.