Siting Desk

Yolo County Battery storage and data center rules.

Battery storage

Ordinance in forceChecked Nov 15, 2026

Key rules
Sec. 8-2.1105 (Ord. 681.236, effective Dec 22, 2022): storage over 2 MW needs a Minor Use Permit in A-N, A-X, A-I, commercial, industrial and PQP zones and is barred in A-C, A-R, residential and park zones; 600 kW to 2 MW needs Site Plan Review outside residential and park zones. Standards: zone setbacks and heights, 60 dBA at the property line of the nearest offsite home, 10 ft vegetation clearance, screening, a decommissioning plan and a removal fund or bond.
Pending action
None found in CEQAnet or news searches.
Projects
Gibson Solar Farm (up to 20 MW AC, Use Permit ZF2020-0043): EIR addendum Apr 1, 2026. CAISO queue: no storage entries.
Sources

Data centers

No data center rulesChecked Nov 16, 2026

Key rules
Title 8 (Land Development and Zoning) and the building and business titles do not mention data centers (GoCodebook copy).
Pending action
None found in agenda, CEQAnet or news searches.
Projects
None found in CEQAnet since 2021.
Sources

A brief on Yolo County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.

Request this briefSee the six productsSolano County sample brief (PDF)