Calaveras County Battery storage and data center rules.
- Battery storageNo battery-specific rules
- Data centersMoratorium
Battery storage
- Key rules
- Title 17 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). BESS goes through a Conditional Use Permit (Double Springs, CUP 2024-086).
- Pending action
- None found in CEQAnet or news searches.
- Projects
- Double Springs Energy Storage (15.2-acre lithium-ion BESS): MND Dec 3, 2025; CUP 2024-086 approved Aug 13, 2026; a second NOD followed Sept 14, 2026. CAISO queue: 1 active storage entry (101 MW), incl. Double Springs Energy Storage.
- Sources
Data centers
- Key rules
- Urgency ordinance imposing a temporary moratorium on approving or developing data centers in the unincorporated county, taken up by the Board Aug 25, 2026; the county filed its CEQA exemption Aug 31. Title 17 (Zoning) does not mention data centers.
- Pending action
- An urgency moratorium lasts 45 days, to about Oct 9, 2026, unless extended. We found no extension vote; confirm with the Planning Department before relying on this row.
- Projects
- None found in CEQAnet since 2021.
- Sources
A brief on Calaveras County.
A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.