Colusa County Battery storage and data center rules.

Battery storage

No battery-specific rulesChecked Nov 15, 2026

Key rules
Chapter 44 (Zoning Code) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Saloon BESS got a Major Use Permit and franchise agreement (PD-25-6).
Pending action
None found in CEQAnet or news searches.
Projects
Saloon BESS (up to 150 MW, near PG&E's Cortina substation, PD-25-6) approved Nov 18, 2025. Janus Solar and Battery Storage use permit approved Feb 25, 2025. CAISO queue: 2 active storage entries (230 MW), incl. Janus, Saloon Energy Storage.
Sources

Data centers

No data center rulesChecked Nov 16, 2026

Key rules
Chapter 44 (Zoning Code) and the building and business titles do not mention data centers (GoCodebook copy, Oct 2026 edition).
Pending action
None found in agenda, CEQAnet or news searches.
Projects
None found in CEQAnet since 2021.
Sources

A brief on Colusa County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.