Siting Desk

Contra Costa County Battery storage and data center rules.

Battery storage

No battery-specific rulesChecked Nov 15, 2026

Key rules
Title 8 (Zoning) has no energy storage provisions (GoCodebook copy, Oct 2026 edition). Small solar plus storage goes through a Land Use Permit (Ranch Sereno, CDLP22-02036).
Pending action
None found in CEQAnet or news searches.
Projects
Opson Solar (Byron, 10 MWh BESS, CDLP25-02033): MND posted Oct 8, 2026. Hubbard Farming and Forestry Clean Power (6.6 MW solar with storage) went to the Byron advisory council Sept 2025. CAISO queue: 5 active storage entries (1,601 MW), incl. Allegheny Energy Storage, Black Diamond ES2, Delilah Energy Storage, Harmony Storage 2; 1 completed.
Sources

Data centers

No data center rulesChecked Nov 16, 2026

Key rules
Title 8 (Zoning) and the building and business titles do not mention data centers (GoCodebook copy, Oct 2026 edition).
Pending action
None found in agenda, CEQAnet or news searches.
Projects
Cities act on their own: Oakley and Richmond have moratoria (Richmond extended its moratorium through Sept 15, 2028), and Pittsburg approved changes for the AVAIO Pittsburg Data Hub backup generating facility (Feb 2026). Pittsburg Technology Park (AVAIO; data center of about 368,551 sq ft in phase 1), approved by the City Council 5-0 in November 2024: the Center for Biological Diversity's CEQA suit settled in December 2025 with added mitigation and $750,000 for climate projects.
Sources

Lawsuits

Checked Nov 16, 2026All cases

A brief on Contra Costa County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.

Request this briefSee the six productsSolano County sample brief (PDF)