No battery-specific rulesChecked Nov 16, 2026

Key rules
Title III (Land Use and Development) has no energy storage provisions (GoCodebook copy, Oct 2026 edition).
Pending action
None for battery storage. The county's data center moratorium, adopted Oct 6, 2026, is in the data center table; an extension is on the Nov 17, 2026 Board agenda.
Projects
Foster Clean Power (Renewable America; 9.4 MWdc solar and a 2.5 MW/10 MWh battery near Arcata), approved by Conditional Use Permit and modified in November 2024, began operating in October 2025 under a contract with the Redwood Coast Energy Authority. CAISO queue: no storage entries.
Sources

Data centers

MoratoriumChecked Nov 16, 2026

Key rules
A 45-day urgency ordinance adopted Oct 6, 2026 (26-949) bars accepting applications for data centers in the unincorporated county. As amended, a data center under 15 MW that runs on 100% on-site renewable power, uses closed-loop cooling and has a water source that does not conflict with public trust resources can still seek a Conditional Use Permit.
Pending action
A 10-month, 15-day extension covering large data centers (26-1110) is on the Nov 17, 2026 Board agenda. Without it the moratorium ends about Nov 20.
Projects
None found in CEQAnet since 2021.
Sources

A brief on Humboldt County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.