Siting Desk

Imperial County Battery storage and data center rules.

Battery storage

No battery-specific rulesChecked Nov 16, 2026

Key rules
BESS approved project by project through Conditional Use Permits, often with a general plan amendment and zone change (Border BESS: CUP24-0027, GPA25-0001, ZC25-0001). No BESS-specific code section found. A one-year cap the Board adopted Dec 9, 2025 limits solar and battery projects on farmland to 7% of the county's agricultural acreage.
Pending action
Border BESS (Apex Energy Solutions, 75 MW) MND, Mar 2026. NorthStar 2 (130 MW solar, 175 MW storage) MND, Apr 2026. Titan II BESS (40 MW) EIR started June 2026. The farmland cap runs one year from Dec 9, 2025; staff were to report back within six months.
Projects
Seville 4 (90 MW solar, 180 MW storage) and Seville 5 (65 MW solar, 130 MW storage) approved by the Board Jan 27, 2026. Big Rock 2 Cluster (Avantus, up to 500 MW solar and 500 MW storage) approved Dec 9, 2025 over the Planning Commission's opposition; the Imperial Irrigation District sued under CEQA. Opt-in: Perkins Renewable Energy (Intersect Power, 1,150 MW solar and 1,150 MW/4,600 MWh storage east of El Centro; 24-OPT-01) is listed as under review; the CEC found the application incomplete Mar 28, 2024, and its page lists no later step. Many projects sit in IID territory, outside the CAISO queue. CAISO queue: 5 active storage entries (1,814 MW), incl. LeConte Energy Storage, Umbriel; 2 completed.
Sources

Data centers

MoratoriumChecked Nov 16, 2026

Key rules
Title 9 lists data centers as a use in the M-1 (inside an enclosed building) and M-2 industrial zones, and Ord. 1616 says they are permitted by right there. The Board adopted a new urgency moratorium 5-0 on Oct 6, 2026, after a Superior Court ruling in August threw out the June 16 moratorium (Ord. 1616) and its July 14 extension (Ord. 1618).
Pending action
The 19-member Data Center Advisory Committee reports in January 2027. Supervisors Escobar and Cardenas-Singh back a ballot measure to ban data centers on unincorporated land; no vote is set. The length of the Oct 6 ordinance is not confirmed: a new urgency moratorium runs 45 days, to about Nov 20, 2026, unless extended.
Projects
Imperial Data Center (Imperial Valley Computer Manufacturing, about 950,000 sq ft on a 75-acre merged site at Aten and Clark roads, next to the city of Imperial): lot merger approved Apr 7, 2026. On Sept 9, 2026 the Superior Court ruled in City of Imperial v. County of Imperial that the county needed CEQA review of the whole project and set aside its November 2025 grading approval. IVCM has said it will seek a new trial, then appeal. The county staff report cites several pending applications in the Mesquite Lake Specific Plan area.
Sources

Lawsuits

Checked Nov 16, 2026All cases

A brief on Imperial County.

A brief covers the rules in force, pending changes, every project proposed in the last five years, how the supervisors voted and the next hearing date, with every claim sourced.

Request this briefSee the six productsSolano County sample brief (PDF)